CHESTERFIELD COUNTY, Va. (WRIC) — Controversy continues to ensue over the construction of Dominion Energy’s proposed natural gas plant — the Chesterfield Energy Reliability Center (CERC ...
CHESTERFIELD COUNTY ... Energy spokesperson Jeremy Slayton said about the proposed Chesterfield Energy Reliability Center. While the county has approved the plan, some Chesterfield residents ...
Dubbed the Chesterfield Energy Reliability Center (CERC), the facility, which is expected to cost $1.47 billion, will generate 944 megawatts of energy. The plant will provide electricity to up to ...
Dominion Energy has asked Virginia officials to approve its request to build a new 1-GW natural gas-fired power plant, as the company seeks to add more generation capacity to help… ...
that it would relocate the proposed “Chesterfield Energy Reliability Center (CERC)” to the Chesterfield Power Station site on Coxendale Road. The new location is just over a mile away from its ...
Construction of the Chesterfield Energy Reliability Center is expected to begin in 2026, with the facility slated to become operational by 2029.
On Thursday, they got their chance. The community group and other county residents asked questions about the Chesterfield Energy Reliability Center at Dominion’s open house. “One of the ...
Dominion Energy wants to build new seven-miles-long high voltage lines in western Chesterfield County in large part to serve a planned hyperscale data center, using four times the electricity the ...
CHESTERFIELD COUNTY, Va. (WRIC) — Chesterfield County residents voiced their steadfast concern and direct opposition on Wednesday to a proposed energy plant that could potentially become a ...